Plannning Commission Approves TIF - March 28, 2016
                                   (Click picture to read article)
Foundations Poured - August 15, 2016
​
Framing Started - September 1, 2016
Trusses Started - September 20, 2016

Below you can follow us along as we work towards the building and launching of the Juniper Village Townhomes.

Project Progress 

Roofing Added - September 26, 2016
Siding - September 26, 2016

Move In Ready